03 / Deliver
WTW / Watson House, Reigate
Deliver
Live building, one team, a clear programme and quality checked at every stage
↑
01 / 14
· Deliver
↓
03.1 / Working in a live building
WTW / Watson House, Reigate
Working in a live building
Business as usual
Similar in-situ refurbishments
Drag to explore ← →






03
Oliver Wyman
Baker Street
↑
02 / 14
· Live building
↓

03.2 / A coordinated local team
A coordinated local team
Phase 1 will move quickly, so we will work as one positive, coordinated and smart local team.
↑
03 / 14
· Local team
↓
LIVE
What our clients say
“Great communication”
“Sensitive to our last-minute requests”
“Positive team members”
“Not like ‘the builders’ were in”
↑
04 / 14
· What our clients say
↓
03.3 / Your project team
WTW / Watson House, Reigate
Your project team

Client
STEVE MITCHELL · DIRECTOR, CRE EUROPE
JO ALFORD · DIRECTOR, CRE EUROPE

Tim Crane
National Director · Project lead · Office and site
Executive sponsor

Phil Hannis
Chief Operating Officer
OFFICE BASED
Client team
STOREY · PROJECT MANAGER
BAP · COST CONSULTANT
VULA · INTERIOR DESIGNER
BEC · SERVICES ENGINEER
01 / Strategy

Danielle Adler
Senior Workplace Consultant
OFFICE BASED

Will Birch
MEP Strategy
OFFICE BASED

Nicola Warburton
Design Studio Manager
MOORGATE STUDIO
02 / Design – Moorgate Studio

Fedor Znak
Lead Designer
OFFICE BASED

Neil Stantiall
Design Co-ordination
OFFICE AND SITE

Nassim Nayeri
Designer
OFFICE BASED
03 / Precon & commercial

Nick Sarl
Furniture Specialist
OFFICE BASED

Emily Henson-Ford
Quantity Surveyor
OFFICE BASED
04 / Delivery

Steve Lea
Delivery Unit Lead
OFFICE AND SITE

Kal Nedyalkov
Project Manager
SITE BASED

Sam Yeboah
Site Manager
SITE BASED
05 / Sustainability & safety

Jamie Richardson
Sustainability Director
OFFICE BASED

Nia Meredith
Head of Standards
SITE AND OFFICE

Sophie Lynch
CSR Co-ordinator
OFFICE AND EVENT
↑
05 / 14
· Project team
↓
03.4 / Key dates
WTW / Watson House, Reigate
Your programme in two phases
Phase 1 moves the Redhill team in during Q2 2027
Phase 1 milestones · December 2026 to April 2027
11 DEC 2026
Contract award
14 DEC 2026
Design kick-off
25 JAN 2027
Contract terms and instruction
1 FEB 2027
Start on site
23 APR 2027
Handover and go-live
01 TENDER AND AWARD · NOV–DEC 2026
2–13 Nov
Client review of tenders
16–20 Nov
Interviews
23–27 Nov
Tender report
30 Nov – 11 Dec
Negotiation and contract award
02 DESIGN AND PROCUREMENT · DEC–FEB
14–18 Dec
Design kick-off and layout freeze
21 Dec – 29 Jan
MEP and architectural design to Stage 4
18–29 Jan
Design pack sign-off
25 Jan
Contract terms and instruction
25 Jan – 19 Feb
Procurement
03 ON SITE · FEB–APR 2027
1 Feb – 9 Apr
Floor 2
8 Feb – 16 Apr
Floor 1
15 Feb – 22 Apr
Ground floor
23 Apr
Phase 1 handover
PHASE 2 · 2027/28
Go-live 24 Feb 2028
8 Dec 2027 – 3 Feb 2028
On site (8 weeks)
28 Jan – 10 Feb 2028
Furniture on site
11–24 Feb 2028
Move-in
SHAPING PHASE 2 IN 2027
Q1
Concept designs and check-in
Q2
Final design detail and Phase 1 reviews
Q3
Contractor proposal for WTW review
↑
06 / 14
· Key dates
↓
03.5 / Programme
WTW / Watson House, Reigate
Your Phase 1 programme
Our Phase 1 programme, from tender review and design development through to handover on 23 April 2027.
NOV 26
DEC 26
JAN 27
FEB 27
MAR 27
APR 27
ACTIVITY
DATES
01 TENDER AND AWARD
Client review of tenders
2–13 NOV
Interviews
16–20 NOV
Tender report
23–27 NOV
Negotiation and contract award
30 NOV–11 DEC
02 DESIGN DEVELOPMENT
Kick-off, GA development and layout freeze
14–18 DEC
MEP detailed design, Stage 3
21 DEC–6 JAN
Architectural and construction, Stage 4
21 DEC–20 JAN
Validation of systems
4–8 JAN
MEP Stage 4 pack
11–29 JAN
Design pack sign-off
18–29 JAN
03 PRE-COMMENCEMENT
Contract terms and instruction
25 JAN
Health and safety, programming and logistics
18–29 JAN
Procurement
25 JAN–19 FEB
04 ON SITE
Floor 2
1 FEB–9 APR
Floor 1
8 FEB–16 APR
Ground floor
15 FEB–22 APR
Phase 1 handover
23 APR
Activity
Milestone
Phase 1 handover
↑
07 / 14
· Programme
↓
03.6 / Managing CAT A services interfaces
WTW / Watson House, Reigate
↑
08 / 14
· CAT A interfaces
↓
03.8 / Risk management
WTW / Watson House, Reigate
Risks and mitigation
Five risks, each with a plan to close it down
Risk rating
High
Medium
Low
01
HIGH
Accurate CAT A design details
Mitigation
Survey all services and voids, and witness MEP commissioning.
02
HIGH
CAT A handover
Mitigation
Work closely with the CAT A team and flag any risks to the CAT B works early.
03
MEDIUM
Working in a live environment
Mitigation
Agree logistics and sequencing early, with clear signage and access plans.
04
MEDIUM
Design agreement
Mitigation
A design schedule with clear sign-off dates, linked to procurement.
05
LOW
Maintaining the modular design principle
Mitigation
Hold to the working wings principle and test the value of every element.
↑
09 / 14
· Risks
↓
03.9 / Quality assurance
WTW / Watson House, Reigate
Checked at every stage
Checked, recorded and signed off as we go
Quality checks from design information through delivery
01
Daily monitoring
02
Fortnightly inspections
03
MEP installation
04
Hidden works
Auditable controls through to final inspection and handover
05
MEP testing
06
Records
07
Final inspection
08
Technical oversight
↑
10 / 14
· Checked at every stage
↓
03.9 / Quality assurance
WTW / Watson House, Reigate
Quality control
Robust management processes, embedded from day one
Key points for every inspection
01
Strip-out
02
MEP and mechanical first fix
03
MEP and mechanical second fix
04
Void closures
05
Snagging
↑
11 / 14
· Quality control
↓
03.9 / Quality assurance
How we deliver quality
01
Strong site leadership
02
Design coordination
03
Programme sequencing
04
Informed subcontractor selection
05
Samples and mock-ups
06
Agreed RFI and approval process
07
Clear specifications
08
Change control
09
Inspection and test plan
↑
12 / 14
· How we deliver quality
↓
03.9 / Quality assurance
WTW / Watson House, Reigate
Right first time
A snag-free handover is planned in, not inspected in at the end
Five principles
01
Design excellence
02
Programme management and sequencing
03
Quality assurance and inspection
04
Progressive snagging and close-out
05
Supply chain accountability
↑
13 / 14
· Right first time
↓
03.9 / The result
WTW / Watson House, Reigate
↑
14 / 14
· The result